Why solar takes 2 to 4 months when the install itself takes a day

The install is the short part

Most residential rooftop systems are physically installed in a single day. If someone has told you the whole project takes a day, they have described one step of about six.

Start to finish, most projects run two to four months, and the large majority of that is waiting on other organisations -- your municipal building department and your utility. Timelines vary meaningfully by jurisdiction, and we cannot guarantee a specific date for exactly that reason.

The actual sequence

First, consultation and design: we look at your bill, your usage and your roof, then design a system around what we find and produce a proposal with an estimated production figure and real pricing.

Then permitting. Plans go to your local building department for review. Turnaround is entirely theirs, and it varies from a jurisdiction that reviews in days to one that takes many weeks. The spread between neighbouring cities can be large -- which is why the crew that handles your project is a certified local team that has already filed in your jurisdiction.

Then installation -- the day on the roof. Then inspection, where a municipal inspector signs off on the work. Then interconnection and permission to operate, where the utility approves the system to export to the grid and swaps the meter if needed. That last step is often the longest single wait, and it is entirely the utility's timeline.

Only after permission to operate can the system legally start producing. We handle the paperwork at every one of those stages, which is the part most people are relieved to hand over, but handling it is not the same as controlling how long it takes.

What actually speeds it up

Complete, accurate plans submitted the first time. A large share of permitting delay is resubmission after a correction notice, and that is avoidable with careful design work up front.

Getting your recent utility bills to us early also helps more than people expect -- accurate usage data means the system is sized correctly the first time, which means fewer revisions downstream.

What does not speed it up is pressure. We will give you an honest estimate of the range for your jurisdiction rather than an optimistic date we cannot hold, because a date we miss is worse for you than a range we meet.

Common questions

How long does solar installation take?+

The physical installation is typically one day for most homes. The full project -- consultation, design, permitting, installation, inspection and utility interconnection -- usually runs two to four months, with most of that time spent waiting on the building department and the utility. Timelines vary by jurisdiction and cannot be guaranteed.

What is permission to operate?+

It is the utility's final approval allowing your system to operate and export to the grid. Until it is granted the system cannot legally start producing. It is often the longest single wait in the process and it runs on the utility's timeline, not the installer's.

Who handles the permits and utility paperwork?+

We do -- permitting, utility applications, inspection scheduling and interconnection paperwork are all included. We cannot control how long each body takes to respond.

Start the clock on the part that takes the longest

Permitting and utility approval are the bulk of the timeline, and they cannot begin until the design is done. The consultation is free and it is the first step of the sequence above.